How to install the Sunrack L-feet

Jan 12, 2018

G-module Installation.

For each use of the G module. You must make sure that: the thread of the screws does not project through the lower side of the G module (max flush).Position the G Module in the rail channel and fasten it loosely with 2 to 3 turns of the screw. The screws can still be freely moved in the rail channel. Slide the screw to their final position in connection with the inter-module lamp ,module end clamp or L feets/hanger bolts and fastens firmly(recommended torque is 8 N.m). As the Figure 1.

1.jpg

Figure 1

L-Feet install with the Rail.

1).L-Feet Pre Installation.

2.jpg

Figure 2

Follow Figure 2 red mark A, keep the M8*25 Bolt no beyond the G module.

2).Install the L-Feet to the roof.

3).Install the Rail

a).

3.jpg

4.jpg

Figure 2

Keep the Bolt in the position as the Figure 2 red mark A,

b).

5.jpg

6.jpg

Figure 4

c).

7.jpg

8.jpg

Figure 5

Keep the Rail on the L-feet Position as the Figure 5

9.jpg

Figure 6

Press the rail and let the G-module in the position as the Figure 6

10.jpg

11.jpg

 Figure 7

Lock the Bolt, let the bolt exceed the G-moudle 3~4mm as the Figure 7 , Remember do not tighten bolt,then the rail and l-feet can be moved per your demand .

d).

12.jpg

Figure 9

Let the rail leave the L-Feet a little Gap, that the rail can adjusted up or down.

13.jpg

14.jpg

Figure 10

Adjusted the Rail in the Position that you want, and fastens firmly.